矿山巷道爆破振动效应对围岩稳定性影响及减振控制措施研究

    Study on the Effect of Blasting Vibration in Underground Roadways on Surrounding Rock Stability and Vibration Control Measures

    • 摘要: 针对深埋巷道爆破掘进引起的振动与围岩变形问题,基于三维数值模拟对不同爆破参数与工程减振措施的效果进行了系统对比。结果表明,延时优化方案(方案B)较原设计方案(方案A)平均峰值振动速度(PPV)降低21.6%,近场降幅20.2%,拱顶下沉量、帮部收敛量及松动圈厚度分别减少21.8%、22.0%和19.8%,稳定性系数提升至1.22;在此基础上引入解耦装药与充气间隔(方案C),各指标降幅进一步扩大至28.5%、27.9%、28.3%和26.1%,近场PPV降至16.2 cm·s−1,稳定性系数提升至1.23。工程措施方面,预裂爆破环(E1)在振动控制上最优,平均PPV降低1.13 cm·s−1;注浆固结圈(E4)在结构加固上最突出,松动圈厚度减少0.154 m、稳定性系数达1.23;隔振空孔环(E3)在中远场振动衰减上占优。组合措施E1+E4+E5可使平均PPV降低26.7%、拱顶下沉减少24.5%、松动圈厚度削减0.172 m、稳定性系数提升至1.25,实现爆破振动抑制、结构变形控制与承载力提升的同步优化。

       

      Abstract: To address vibration and surrounding rock deformation induced by deep underground roadway blasting excavation, a three-dimensional numerical simulation was conducted to systematically compare the effects of different blasting parameters and engineering vibration control measures. The results show that the delay-optimization scheme (Scheme B) reduced the average peak particle velocity (PPV) by 21.6% compared with the original design (Scheme A), with a 20.2% reduction in the near field. The roof settlement, sidewall convergence, and loose zone thickness decreased by 21.8%, 22.0%, and 19.8%, respectively, and the stability coefficient increased to 1.22. With the introduction of decoupled charging and air-decking (Scheme C), the reductions in these indicators were further increased to 28.5%, 27.9%, 28.3%, and 26.1%, respectively, with near-field PPV reduced to 16.2 cm·s−1 and the stability coefficient increased to 1.23. Among the engineering measures, the pre-split blasting ring (E1) achieved the best vibration control, reducing the average PPV by 1.13 cm·s−1; the grouting reinforcement ring (E4) showed the best structural strengthening effect, reducing the loose zone thickness by 0.154 m and increasing the stability coefficient to 1.23; the isolation blasthole ring (E3) exhibited superior vibration attenuation in the middle and far fields. The combined measures of E1+E4+E5 reduced the average PPV by 26.7%, roof settlement by 24.5%, and loose zone thickness by 0.172 m, and increased the stability coefficient to 1.25, achieving simultaneous optimization of vibration suppression, deformation control, and load-bearing capacity enhancement.

       

    /

    返回文章
    返回