厚煤层大断面巷道切顶锚索补强支护技术研究

    Research on Top Cutting and Anchor Cable Reinforcement Support Technology for Thick Coal Seam Large Section Roadways

    • 摘要: 针对厚煤层大断面巷道围岩控制难题,本文以镇城底矿18106运输顺槽为工程背景,运用理论分析、数值模拟及现场试验方法,提出“爆破预裂切顶卸压+锚索补强支护”技术优化方案。研究揭示:18106运输顺槽煤柱侧向支承应力呈现非对称“马鞍形”分布特征,且两侧垂直应力分布存在显著差异性。相较传统锚杆支护体系,新型支护优化方案显著改善巷道围岩收敛特征,顶板、煤壁帮及煤柱帮表面最大平均收敛量降幅均达20%以上。现场监测数据表明,采用切顶锚索协同支护体系后,大断面巷道围岩稳定性得到显著提升。

       

      Abstract: In response to the difficulty of controlling the surrounding rock of thick coal seam and large section roadway, this paper takes the 18106 transportation channel of Zhenchengdi Mine as the engineering background, and uses theoretical analysis, numerical simulation, and field test methods to propose an optimized technical scheme of "blasting pre splitting cutting top pressure relief+anchor cable reinforcement support". Research has revealed that the lateral support stress of the 18106 transport chute coal pillar exhibits an asymmetric "saddle shaped" distribution characteristic, and there are significant differences in the vertical stress distribution on both sides. Compared with the traditional anchor rod support system, the new support optimization scheme significantly improves the convergence characteristics of the surrounding rock in the roadway, with a maximum average convergence reduction of over 20% for the roof, coal wall, and coal pillar surfaces. On site monitoring data shows that the stability of the surrounding rock in large section tunnels has been significantly improved after the use of the roof cutting anchor cable collaborative support system.

       

    /

    返回文章
    返回